Close

LCY Ledger Building

Portfolio | Electrical Contractor

LCY Ledger Building

Complete Electrical and Mechanical installation works for the new ground services site village at London City Airport.

Role: M&E Contractor

Work Involved:

Provision of a new mains services substation which also incorporated main data and power provisions. Once the site village was fully installed, tested and operational, we completed the M&E strip out of the existing Ledger Building, prior to demolition.

Our responsibility for the project encompassed liaison with and management of the following London City Airport departments and contractors:

  • UK Power Networks
  • NATS
  • Main Security Camera Contractors
  • Face Recognition Contractors
  • Data / IT Contractor
  • Airfield Lighting Contractor
  • Fire Alarms Contractor

All works were completed within the agreed time frame and budget.