Management of the installation of welfare and office cabins involving the survey of existing MEP services in the site area and appointment of subcontractors to carry out required Civil works package.
BP Installations carried out the full MEP works (1st/2nd fix) and Life Services. As part of the project, works were carried out to install two underground sceptic waste tanks. In addition, BP Installations were responsible for arranging, taking delivery of and positioning of fifty portacabin offices and managing the internal fit out of the portacabins as required by the other trade contractors.
External Works
BPI programmed the sequence of works to design and build the concrete ring beams to support the new portacabin offices. Separate toilets, shower cubicle block and Cafeteria were also supplied; all units were craned into position.
Further works involved the provision of mains and secondary power, Public Health Services and the creation of a Tarmac surface area external to the newly installed portacabins.
As part of the project, we provided as-built drawings, and MEP / Life services Hand over certification.
LCY / Bechtel / Sub Contractors moved into the new accommodation on programme.